In the Kallonlahti POPRAMP project, a 64 metres long loading ramp will be built using retaining quay wall elements at the Port of Pori.Work on the site will commence in […]
Terramare’s dredger Meri-Pekka has excavated the seabed at a depth of 43 metres for the Tahkoluoto offshore wind farm expansion project. The purpose of the test excavations was to test […]
Terramare celebrated the closing seminar of a six-month occupational safety training called NINA Expedition at Suomenlinna (sea fortress), Finland. The NINA Expedition is a Boskalis wide ‘learning‐by‐doing’ program that aims […]
The quay to be constructed is a 144 metres long retaining wall structure. The contract also includes approximately 40,000 m3 of dredging works. Work on the site will commence in […]
We support volunteer work related to maintaining maritime safety. Terramare donated charity funds to the Helsinki Sea Rescue Society. Each safety observation made at Terramare’s construction site in 2022 contributed […]
The quay structures and mooring points required by the LNG terminal vessel to be situated at the Port of Inkoo have been completed as planned. The LNG terminal vessel due […]
The quay projects undertaken by Terramare for the Kallonlahti 2 quay and the Tahkoluoto liquid bulk quay have been completed. The new 91-metre-long liquid bulk quay replaced a 60-year-old caisson-type […]
Ambassador Govert Jan Bijl de Vroe and Policy Officer for Trade & Innovation Miina Ojanperä from the Embassy of the Netherlands visited Terramare’s head offices at Keilaniemi in October. The […]
The Vuosaari fairway and harbour basin deepening project was awarded this year with an honourable mention at the Association of Project Professionals Finland’s Project Days on 25 October. Terramare implemented the […]
Our office is located on the 3rd floor of the stylish HTC Keilaniemi Waterfront office building with a spectacular sea view. We are located along excellent transport connection. We are easy to reach by bus, car and metro.
The 60-year-old caisson-type quay structure at Pori’s Tahkoluoto oil harbour will be demolished and a new retaining quay wall will be constructed in its place. At the same time, the […]
The contract concerns the construction of approximately 500 metres of retaining wall quay at the D0 and D2-3 quay berths in the D section of Mussalo Harbour. The project includes […]