Terramare to expand the Port of Rauma


2 October 2019

Terramare has signed a contract with the Port of Rauma on 30 September 2019 for the construction of Petäjäs phase 4. The contract includes dredging works of contaminated soil at Petäjäs sea area, soil replacement dredging works, as well as the construction of the upcoming harbour field. The amount of dredged masses is about 300,000 m3. The dredging works are executed by the dredger Kahmari 2 and by the towable barges SCG 3,4,5 ja 6.

The port area will be filled and deep compacted with blasted rock of around 800,000 m3. In addition, public utility service will be constructed.

The works will commence during October and are scheduled to be completed by 31 October 2021.

The contract value is about EUR 15.5 million.

TERRAMARE OY


Further information, please contact:
Hannu Tomperi, Managing Director, tel. +358 40 517 6214