Terramare to construct a coal jetty extension at Port of Naantali


2 August 2019

 

Terramare Oy has signed a contract with Port of Naantali on 28 June 2019 for the construction of a 60 metre long and 20 metre wide concrete jetty extension founded on bored piles.

The works will commence during August and are scheduled to be completed by 30 April 2020.

The site employs a total of approximately 10 employees.

The contract value is about EUR 3.4 million.